As of October 2019, Refined (Lindfield – Builder Northpoint) located at 51-55 Lindfield Avenue, Lindfield, NSW has completed the following works:

  • Bulk excavation progressing – approximately 80% complete.
  • Bulk excavation near the final level at the Lindfield Avenue end of the site. Working back towards the Havilah Lane side.
  • 3rd drop of shotcrete completed to the Lindfield Avenue end of the site
  • 2nd drop of shotcrete completed to the North and South ends of the site
  • 1st drop of shotcrete completed to the Havilah Lane end of the site
  • All temporary shoring anchors complete.
  • Substation due to be energized this week.

On site photos:

  • Shoring wall face was finished with nice and smooth finish after shotcrete completed.

WechatIMG7

  • Bulk excavation activity is underway as per program.

WechatIMG15

  • Cast-in drainage duct prevents the shoring wall from issue caused by underground water seepage in basement.