We are delighted to present you with an update on the remarkable progress of Verset Stage 2 for this month!

As of June 2023, Verset Stage Two, Rouse Hill has completed the following works:

  • All buildings are topped out – all slab pours have been completed.
  • Wall framing works are progressing in all buildings.
  • In Building H, wall sheeting is up to L3 and ceiling sheeting is up to L2
  • In Building G, services rough-in and window installation have commenced.

Additional exciting news!

The display unit at Verset Stage Two is nearing completion. Stay tuned for an exclusive preview.