We are excited to provide you with the latest updates on Mayrin Group’s Archwood Residences.

Block C: Steel frame completed, roof sheeting 50% completed, and hydraulic and electrical rough-in up to L2.

Block F: Slab extensions completed, scaffold installation completed, and steel framing up to L1.

Block E: Ground floor steel framing and lift shafts installed, scaffold installation and Level 1 floor joist completed.

Block A/B: Ground floor steel framing and wall panel installation are almost complete.

Block D: GF slab poured.

We are proud of the progress made on the Archwood Residences and are committed to keeping you informed throughout the process.