We are delighted to present you with an update on the remarkable progress of Verset Stage 2 for this month!
As of June 2023, Verset Stage Two, Rouse Hill has completed the following works:
- All buildings are topped out – all slab pours have been completed.
- Wall framing works are progressing in all buildings.
- In Building H, wall sheeting is up to L3 and ceiling sheeting is up to L2
- In Building G, services rough-in and window installation have commenced.
Additional exciting news!
The display unit at Verset Stage Two is nearing completion. Stay tuned for an exclusive preview.
We are committed to keeping you well-informed and involved throughout this journey. As the construction progresses, we will continue to share updates and celebrate milestones. Our dedicated customer service team is always available to assist you with any questions or provide further information.
Thank you for selecting Verset Stage Two as your future home. Stay tuned for more thrilling updates!
For more information: verset.com.au | 1800 093 355
0 comments
Here is no comments for now.