We are pleased to present our monthly construction update for Stage Two of Verset. Here is a summary of our progress as of November 2023:
- External blockwork is almost finished.
- Planters are being filled in Buildings F and G.
- Building H’s podium has started being planted.
- Footpath works are ongoing.
- Building H’s lobbies are almost complete.
- All kitchens are installed.
- Timber flooring is complete in H, G, and F.
Stay tuned for more updates. Thank you for your continued support and trust in us. We can’t wait to welcome you to your new home!