We are delighted to share the latest updates on the ongoing construction at The Archwood Residences townhouses. Here’s a summary of the significant progress achieved as of October 2023:
Completed Works:
- Blocks D, F, E, C, and G: Lightweight Steel and Structural Steel with Lift Shafts have been entirely completed, signifying a substantial milestone in the construction process.
- Blocks AB: Lightweight Steel and Structural Steel with Lift Shafts are currently at 50% completion, progressing steadily according to the project schedule.
- Brickwork Progress: Block C’s brickwork is fully completed and undergoing the cleaning phase. Block F’s brickwork is finished, while Block E stands at 80% completion, with cleaning in progress.
- Windows Installation: The progress in Block C has reached 30% completion.
- Internal Partitioning: Significant progress has been achieved in Block C, with Level 2 at 70%, Level 1 at 20%, and Ground Floor at 20% completion concerning internal partitioning.
- Balcony Waterproofing: Waterproofing Block C’s balconies has reached 50% completion.
We’re pleased to share these significant advancements at Archwood Residences. Stay updated for further developments.
Please do not hesitate to contact us for more information or to schedule a VIP appointment at www.thearchwood.com.au or call 1800 17 1188.
![](https://i0.wp.com/mayringroup.com.au/wp-content/uploads/2023/11/DJI_0832.jpg?resize=1024%2C576&ssl=1)
![](https://i0.wp.com/mayringroup.com.au/wp-content/uploads/2023/11/DJI_0833.jpg?resize=1024%2C576&ssl=1)
![](https://i0.wp.com/mayringroup.com.au/wp-content/uploads/2023/11/WechatIMG749.jpg?resize=1024%2C768&ssl=1)
![](https://i0.wp.com/mayringroup.com.au/wp-content/uploads/2023/04/Copy-of-Clean-Real-Estate-Instagram-Post.jpg?resize=1024%2C1024&ssl=1)
![](https://i0.wp.com/mayringroup.com.au/wp-content/uploads/2023/03/Archwood-01.jpg?resize=1024%2C556&ssl=1)
0 comments
Here is no comments for now.