We are excited to provide you with the latest updates on Mayrin Group’s Archwood Residences.
Block C: Steel frame completed, roof sheeting 50% completed, and hydraulic and electrical rough-in up to L2.
Block F: Slab extensions completed, scaffold installation completed, and steel framing up to L1.
Block E: Ground floor steel framing and lift shafts installed, scaffold installation and Level 1 floor joist completed.
Block A/B: Ground floor steel framing and wall panel installation are almost complete.
Block D: GF slab poured.
We are proud of the progress made on the Archwood Residences and are committed to keeping you informed throughout the process.
Please do not hesitate to contact us for more information or to schedule a VIP appointment at www.thearchwood.com.au or by calling 1800 17 1188.
On-site construction photos:
0 comments
Here is no comments for now.