We are pleased to present our monthly construction update for Stage Two of Verset. Here is a summary of our progress as of October 2023:
- External blockwork is currently in progress across all buildings.
- External waterproofing is being carried out in all external areas.
- Appliance installation in Building H has been completed.
- Timber flooring has been completed in Building H and is ongoing in Buildings E, F, and G.
- Kitchen installation is completed in Buildings G and H and ongoing in Buildings E and F.
- The initial cleaning is set to commence very soon in Building H.
Stay tuned for more updates. Thank you for your continued support and trust in us. We can’t wait to welcome you to your new home!