We are pleased to provide you with an update on the progress of Verset Stage 2 for the month of April. Our team continues to work tirelessly to ensure that every aspect of the project is executed perfectly, and we are happy to share our latest construction update with you.
We are delighted to announce that Building H has reached topping-out milestone, marking a significant achievement for our team. Additionally, external walls and framing are progressing to Level 2, while services rough-ins are taking place on the ground floor and Level 1. Our team is now preparing the balconies for paint, adding the finishing touch to this stunning building.
Building G will be pouring Level 3 slab and Building F will be pouring Level 2 slab in early May.
Moreover, Building E’s Level 1 has been poured, and we are currently working on formwork for Level 2. We remain dedicated to delivering a high-quality project and are proud of our team’s hard work and commitment to excellence. We are committed to ensuring timely completion.
Thank you for your continued support and interest in our progress. Stay tuned for more updates as we continue to make progress towards completing Verset Stage 2.
For more information and private inspection: www.verset.com.au or 1800 093 355
On-site construction photos:
0 comments
Here is no comments for now.