Great news for March! The construction progress at The Archwood Residences townhouses is continuing to move forward seamlessly. Here are some exciting updates for the month:

• The Ground Floor slab of Block C has been poured, and the steel frame erection has commenced.

• Most of the Ground Floor slab for Block A and B has been poured.

• The spoil from Block D has been moved to the central courtyard, and the retaining wall is completed.

• OSD pours and waterproofing have been completed.

• Driveway has been poured.

At Archwood Residences, we are committed to ensuring that each unit is built to the highest standards of quality and craftsmanship. We will continue to provide regular updates as we work towards completing this exciting project. Stay tuned for more news and progress updates!