As of October 2022, The Archwood Residences (Builder-Growthbuilt) Roseville has completed the following works:

—Area 1 basement slab completed

—Area 1 Upper slab formwork close to complete

—Area 2 in-ground services completed

—Area 2 lift pits and footings completed

—Area 3 binding layer installed

Continue to watch this space for further updates on our exquisite The Archwood Residences project.