We are pleased to provide the latest progress report on the construction of Archwood Residences Townhouse as of February. Here’s a summary of the progress made in each block:
Blocks A/B:
- Rough-ins for electrical, mechanical, fire, and hydraulic services are nearing completion.
- Brickwork is 50% complete.
- Subsill/Subhead work is 40% complete.
Block C:
- Fire services have been installed.
- External brickwork is complete.
- External stone cladding is 80% complete.
- Work is in progress on electrical, hydraulic, and flooring systems.
- Door installation is ongoing.
- Irrigation and waterproofing are ongoing.
Block D:
- Electrical, mechanical, and fire service cut-outs are halfway completed.
- Floor screeds have been laid.
- Secondary waterproofing work is underway.
- Windows and external cladding are 80% complete.
Block E:
- All electrical, mechanical, and fire service cut-outs are complete.
- Floor tiling and louvres to the South have been installed.
Block F:
- Electrical, mechanical, and fire service cut-outs are complete.
- Louvres to the South have been installed.
- Tiling work is ongoing.
- Kitchen installation is in progress.
Block G:
- Electrical, mechanical, and fire service cut-outs are halfway completed.
- Floor screeds are installed.
- Secondary waterproofing is ongoing.
- External cladding is 80% complete.
Stay tuned for further updates on this exquisite project. For more information, you can visit thearchwood.com.au or call 1800 171 118.