The Archwood Residences (Roseville – Builder Growthbuilt) Monthly Updates – July 2022

As of July 2022, The Archwood Residences (Builder-Growthbuilt) Roseville has completed the following works:

1. 80% of the excavation work has been completed and a total of 30,000 tonnes of soil has been removed from the site.

2. The Crane has been erected and is now operational

3. Upgrading of the stormwater pipes has been completed.

4. The retaining wall near Boundary St has been constructed

5. Construction of the retaining wall for the D townhouse has commenced and the foundations have been poured

6. The first phase of the shotcrete basement wall reinforcement is nearing completion.

7. The piling for basement structure has been completed.