Creating a new address takes time, despite the extreme wet weather, we maintained our construction progress by dewatering and sequencing measures.

The Archwood Residences has managed to make immense headway in the following areas:

1. Shotcrete Drop 1 is completed

2. Shotcrete Drop 2 is 70% completed

3. Shotcrete Drop 3 is 80% completed

4. Stormwater upgrade is completed

5. Temporary Bracing is completed

6.  Anchor & stressing is 95% completed

7. Bulk Excavation is 95% completed

For more information: thearchwood.com.au| 1800 171 118