As of November 2022, Verset Stage II (Builder-Westbourne Construction) Rouse Hill has completed the following works:

-Pour 1 (first building) Ground floor slab is complete.

-Pour 3 basement slab is complete.

– Pour 4,5 and 6 basement slabs are in progress.

-All ground services are complete.

-OSD tank concrete pour is in progress.

Continue to watch this space for further updates on our Verset Stage II project, as it is sure to outdo its predecessor.