We are excited to share the latest construction updates for The Archwood Residences. As of September 2024, we have made significant progress in each block, with all construction moving forward seamlessly.
Block A/B
• Sandstone work: 80% complete
• Mechanical fit off: 100% complete
• Plumbing fit off: 95% complete (except Lot 1)
• Electrical fit off: 95% complete
• Mechanical systems: 95% complete (except Lot 1)
• Timber flooring: 90% complete
• Internal tiling: 100% complete
• External tiling: 15% complete
Block C
• Final cleaning: 100% complete
• Courtyard paving: 100% complete
Block D & G
• Wet area tiling: 100% complete
• Pendant lighting: 100% complete
• Electrical fit off: 100% complete
• Plumbing fit off: 100% complete
Block E & F
• Tiling: 100% complete
• Mechanical systems: 100% complete
• Electrical commissioning: 100% complete
• Plumbing fit off (Blocks F and E): 100% complete
• Timber flooring: 100% complete (except basement)
Discover the elegance of The Archwood Residences—our showroom is now open. Secure your private tour today by calling 1800 171 188.