We are delighted to share the latest updates on the ongoing construction at The Archwood Residences townhouses. The construction progress is going beautifully this month.
As of May 2024, we have completed the following work in each block:
Block AB –
Internal Sheeting is 90% complete
Façade Brickwork is complete
Windows installation is 95% complete
External Cladding is complete
Block C –
Electrical, hydraulic, mechanical services fit-off is 90% complete
Fire services is complete
Flooring, stone tops, door installation is complete
FF&E is 90% complete
Scaffold strip and Brickwork is complete
Stone cladding is 95% complete
Irrigation is complete
Planters waterproofing is complete
Block D & G –
Internal tiling is nearly complete
Kitchens installation is 80% complete
Door Installation is 80% complete
Fire service is complete
Windows installation is 90% complete
Façade works and fit-off is 80% complete
Scaffold strip is complete
Block E –
Internal flooring is complete
Internal tiling is 98% complete
Kitchen installation is 60% complete
Door installation is complete
Fire service is complete
Scaffold strip is complete
Façade fit-off is 80% complete
Planter brickwork is 80% complete
Block F –
Internal flooring, tiling, door installation is complete
Joinery with stone tops is 75% complete
Electrical and mechanical services fit-off is 70% complete
Hydraulic services fit-off is 80% complete
Fire service is complete
Scaffold strip and façade fit-off is complete
Planter brickwork is 80% complete
Thank you for your continued support as we make significant strides towards the completion of The Archwood Residences townhouses. Stay tuned for more updates next month!
For more information, you can visit thearchwood.com.au or call 1800 171 118.