As of Aug2020, Refined (Lindfield – Builder Northpoint) located at 51-55 Lindfield Avenue, Lindfield, NSW has completed the following works:
FIT OFF / INTERNAL WORK
Ground Floor:
- Final Paint complete
- Appliance installation commenced
Level 1:
- Timber flooring installation complete
- Skirting installation complete
- Appliance installation commenced
Level 2:
- Kitchen Install and stone complete
- Bathroom and Laundry tiling complete
- Bathroom fit off near complete
- Shower screen installation complete
- Electrical Fit Off complete
- Timber flooring installation complete
- Skirting installation complete
- Appliance installation commenced
Level 3:
- Kitchen Install and stone complete
- Bathroom and Laundry tiling complete
- Bathroom fit off near complete
- Shower screen installation complete
- Electrical Fit Off complete
- Timber flooring installation complete
- Skirting installation commenced
- Appliance installation commenced
Level 4:
- Painting undercoat and first coat complete
- Kitchen Install complete
- Stone Installation near complete
- Bathroom and Laundry tiling complete
- Bathroom fit off near complete
- Shower screen installation near complete
- Electrical Fit Off commenced
- Timber flooring installation commenced
Level 5:
- Painting undercoat and first coat complete
- Aluminium window and door installation complete
- Bathroom and laundry waterproofing complete
- Bathroom and laundry tiling near complete
- Kitchen installation commenced
Level 6:
- Painting undercoat and first coat complete
- Aluminium window and door installation complete
- Bathroom and laundry waterproofing complete
- Bathroom and laundry tiling near complete
- Kitchen installation commenced
EXTERNAL:
Havilah Building:
- Render and painting complete to the Havilah Lane from levels 1 to the roof.
- Cladding complete to Havilah Lane Building
- Scaffold removed to the south elevation and west elevation.
- Balcony tiling complete on levels 1 – 3
- Composite decking complete to the balconies on levels 1 – 3
- Balustrade installation complete
Lindfield Building:
- Lindfield Avenue Building Render and painting near complete from level 1 – roof
- Cladding complete to the south elevation
- Roof waterproofing complete
- Balcony tiling near complete from levels 2 – 4
- Balcony timber decking near complete from levels 2 – 4
North Building:
- Cladding near complete to the East end of the North Building
- Balustrade installation commenced
- Roof waterproofing complete to the western roof
- Planterbox waterproofing complete to the common area roof terrace
- Tiling commenced to the roof terrace in the Air Conditioning enclosure
- Balcony tiling near complete from levels 1 – 3
- Balcony timber decking commenced
Visit Our Display Room at G01/51-55 Lindfield Ave, Lindfield, NSW 2070