As of Aug2020, Refined (Lindfield – Builder Northpoint) located at 51-55 Lindfield Avenue, Lindfield, NSW has completed the following works:

FIT OFF / INTERNAL WORK

Ground Floor:   

  • Final Paint complete
  • Appliance installation commenced

Level 1:

  • Timber flooring installation complete
  • Skirting installation complete
  • Appliance installation commenced

Level 2:

  • Kitchen Install and stone complete
  • Bathroom and Laundry tiling complete
  • Bathroom fit off near complete
  • Shower screen installation complete
  • Electrical Fit Off complete
  • Timber flooring installation complete
  • Skirting installation complete
  • Appliance installation commenced

Level 3:

  • Kitchen Install and stone complete
  • Bathroom and Laundry tiling complete
  • Bathroom fit off near complete
  • Shower screen installation complete
  • Electrical Fit Off complete
  • Timber flooring installation complete
  • Skirting installation commenced
  • Appliance installation commenced

Level 4:

  • Painting undercoat and first coat complete
  • Kitchen Install complete
  • Stone Installation near complete
  • Bathroom and Laundry tiling complete
  • Bathroom fit off near complete
  • Shower screen installation near complete
  • Electrical Fit Off commenced
  • Timber flooring installation commenced

Level 5:

  • Painting undercoat and first coat complete
  • Aluminium window and door installation complete
  • Bathroom and laundry waterproofing complete
  • Bathroom and laundry tiling near complete
  • Kitchen installation commenced

Level 6:

  • Painting undercoat and first coat complete
  • Aluminium window and door installation complete
  • Bathroom and laundry waterproofing complete
  • Bathroom and laundry tiling near complete
  • Kitchen installation commenced

EXTERNAL:

Havilah Building:

  • Render and painting complete to the Havilah Lane from levels 1 to the roof.
  • Cladding complete to Havilah Lane Building
  • Scaffold removed to the south elevation and west elevation. 
  • Balcony tiling complete on levels 1 – 3
  • Composite decking complete to the balconies on levels 1 – 3
  • Balustrade installation complete

Lindfield Building:

  • Lindfield Avenue Building Render and painting near complete from level 1 – roof
  • Cladding complete to the south elevation
  • Roof waterproofing complete
  • Balcony tiling near complete from levels 2 – 4
  • Balcony timber decking near complete from levels 2 – 4

North Building:

  • Cladding near complete to the East end of the North Building
  • Balustrade installation commenced
  • Roof waterproofing complete to the western roof 
  • Planterbox waterproofing complete to the common area roof terrace
  • Tiling commenced to the roof terrace in the Air Conditioning enclosure
  • Balcony tiling near complete from levels 1 –  3
  • Balcony timber decking commenced